The information below summarizes the case you selected.

Case Number: BLD2017-47984
 
Status: Finaled
Name: CALIFORNIA'S GREAT AMERICA
Address:
 
Application Date: 9/1/2017
Description: 3RD PARTY PHASED PERMIT - Complete permit issuance //
1/18/2018 STRUCTURAL 10/3/2017 FOUNDATION ONLY -
CONSTRUCTION OF (N) SUPERSTRUCTURE COASTER,
CALLED "RAILBLAZER", NEW BUILDING # 541 REQUESTED
 
Activities

 
APPLICATION RECEIVED
Assigned to: Not Assigned
Done by:
Status: Done Date Received: 9/1/2017

Created by Online Portal on 09/01/2017 at 16:17 PM
 
603 THIRD PARTY PLAN CHECK
Assigned to: Ket Le Sent to 3rd Pty: 9/1/2017
Done by: Ket Le 3rd Pty Appr.:
Status: Done Appr. plans rec'd: 9/29/2017

ONLINE STRUCTURAL 3RD PARTY REVIEW - BOLEY
 
608d BLDG PLAN REV REG.
Assigned to: Ket Le SUBMITTAL: 9/1/2017
Done by: Ket Le TARGET: 10/3/2017
Status: Done END DATE: 9/29/2017

ONLINE STRUCTURAL 3RD PARTY REVIEW - BOLEY
 
612 PLANNING REVIEW
Assigned to: DATE SENT: 9/1/2017
Done by: RECEIVED: 9/1/2017
Status: Done COMPLETE: 9/29/2017

ONLINE - Stamp transfer required
 
632 FIRE REVIEW
Assigned to: Not Assigned DATE SENT: 9/1/2017
Done by: RECEIVED: 9/1/2017
Status: Done COMPLETE: 1/25/2018

Issued permit under FIR17-1190, Rev. 1 on 1/25/18
Structural Ok to release - DP- 1/17/18
ONLINE - Foundation OK to release - DP
copy of receipt and print screen in pick up.

 
652 WATER REVIEW
Assigned to: Not Assigned DATE SENT: 9/1/2017
Done by: RECEIVED: 9/1/2017
Status: Done COMPLETE: 9/27/2017

09/27/17 - OK to issue permit. No requirements from Water Dept. Per site visit
BFPs are above ground. HM

ONLINE

 
642 ENGR REVIEW
Assigned to: Not Assigned DATE SENT: 9/1/2017
Done by: RECEIVED: 9/1/2017
Status: Done COMPLETE: 9/6/2017

NEDRAT

ONLINE

 
601a REVISIONS SUBMITTED
Assigned to: Ket Le Received: 9/13/2017
Done by: Ket Le
Status: Done Completed: 9/29/2017

KLE, routed 3 sets of plans (REVISIONS), 2 sets of calcs- Foundation, 2 sets
of calcs- Section C Foundation, 2 sets of calcs- Column Anchorage, 1 set C-10
Form

Contact: Lowell Esposo, 408-986-5874, lowell.esposo@cagreatamerica.com

 

 
633 FIRE REVIEW COMMENTS
Assigned to: Not Assigned DATE SENT: 9/20/2017
Done by:
Status: Done RESPONSE: 9/20/2017

Structural Ok to release - DP- 1/17/18
Foundation OK to release - DP 9/20/17

 
(F) ISSUE PARTIAL PERMIT
Assigned to: Not Assigned
Done by: 10/3/2017
Status: Done Date issued: 10/3/2017
 
 
104 REBAR
Assigned to: Date requested: 10/11/2017
Done by: Date due: 10/16/2017
Status: Partial Approval Date done: 10/17/2017

Scheduled by a contractor via Hello! on 10/11/2017 at 08:38:47. Contact: (831)
212-4355.
Cages # C5; C6; C25; C26; C27; C28; C29; C30; C44; C45; C47; C43; C8; C4;
C31A; C42 and C46 total of 17 cages -OK highlight in yellow on page S2.1

 
101 FOUNDATION
Assigned to: Date requested: 10/13/2017
Done by: Date due: 10/17/2017
Status: Partial Approval Date done: 10/17/2017

Scheduled by a contractor via Hello! on 10/13/2017 at 08:56:43. Contact: (831)
212-4355.
Cages # C3; C7; C9; C10; C21; C2822; C23; C32; C33; C48; C49 total of 11
cages -OK highlight in green on page S2.1

 
101 FOUNDATION
Assigned to: Date requested: 10/16/2017
Done by: Date due: 10/18/2017
Status: Fail Date done: 10/18/2017

Scheduled by a contractor via Hello! on 10/16/2017 at 07:25:43. Contact: (831)
212-4355.
not ready

 
104 REBAR
Assigned to: Date requested: 10/17/2017
Done by: Date due: 10/20/2017
Status: Partial Approval Date done: 10/20/2017

Scheduled by a contractor via Hello! on 10/17/2017 at 09:22:20. Contact: (831)
212-4355.
Total of 24 cages C34; C11; C20; C41; C41B; C40; C19; C12; C2; C50; C35;
C36B; LB2; C12B; C18; C1; C36; C51; C58; C13; C17; C57; C15B; C56 - OK
see page S2.1 highlight in orange

 
104 REBAR
Assigned to: Date requested: 10/18/2017
Done by: Date due: 10/23/2017
Status: Cancelled Date done: 10/20/2017

Disp set to [CNCL] by a contractor via Hello! on 10/20/2017 at 13:59:38.
 
101 FOUNDATION
Assigned to: Date requested: 10/19/2017
Done by: Date due: 10/24/2017
Status: Cancelled Date done: 10/23/2017
 


Scheduled by a contractor via Hello! on 10/19/2017 at 13:22:24. Contact: (831)
212-4355.

10/23 - Canceled per Cameron Kinder. //MPEY

 
104 REBAR
Assigned to: Date requested: 10/20/2017
Done by: Date due: 10/25/2017
Status: Partial Approval Date done: 10/25/2017

Scheduled by a contractor via Hello! on 10/20/2017 at 14:01:04. Contact: (831)
212-4355.
reinforcing cages, per specifications- 10 locations OK, as noted on card, and
see pink highlighting for locations.

 
104 REBAR
Assigned to: Date requested: 10/23/2017
Done by: Date due: 10/27/2017
Status: Partial Approval Date done: 10/27/2017

Scheduled by a contractor via Hello! on 10/23/2017 at 15:06:46. Contact: (831)
212-4355.
9 spiral cages/caisons OK as indicated on permit card, and highlighting on
plans.

 
104 REBAR
Assigned to: Date requested: 10/25/2017
Done by: Date due: 10/30/2017
Status: Fail Date done: 10/30/2017

Scheduled by a contractor via Hello! on 10/25/2017 at 09:16:02. Contact: (831)
212-4355.
Contractor declined inspection

Not ready:

 
101 FOUNDATION
Assigned to: Date requested: 10/27/2017
Done by: Date due: 11/1/2017
Status: Partial Approval Date done: 11/1/2017

Scheduled by a contractor via Hello! on 10/27/2017 at 10:59:21. Contact: (831)
212-4355.
Pile caps and grade beams for piles C27; C45; C44; C26; C6; C28; C5; C29;
C30 (total of 9) - OK highlight in green on page C2.1
No conduits allowed to install along grade beam without EOR approval

 
101 FOUNDATION
Assigned to: Date requested: 10/30/2017
Done by: Date due: 11/2/2017
Status: Fail Date done: 11/2/2017

Scheduled by a contractor via Hello! on 10/30/2017 at 08:12:56. Contact: (831)
212-4355.

Not ready:

 
104 REBAR
Assigned to: Date requested: 11/2/2017
Done by: Date due: 11/7/2017
Status: Fail Date done: 11/7/2017

Scheduled by a contractor via Hello! on 11/02/2017 at 15:06:01. Contact: (831)
212-4355.

Not ready:

 

 
104 REBAR
Assigned to: Date requested: 11/3/2017
Done by: Date due: 11/8/2017
Status: Fail Date done: 11/8/2017

Scheduled by a contractor via Hello! on 11/03/2017 at 14:50:15. Contact: (831)
212-4355.
Pile cap located off set of C4 pile- Provide RFI from EOR
Provide RFI from EOR regarding conduits running inside along the grade beam
Grade beam excavation shall be clean of any loose dirt and have min 3┐
clearance to earth
All grade beams reinforcement into pile cap shall be completed prior inspection
n

 
101 FOUNDATION
Assigned to: Date requested: 11/6/2017
Done by: Date due: 11/9/2017
Status: Partial Approval Date done: 11/9/2017

Scheduled by a contractor via Hello! on 11/06/2017 at 09:44:13. Contact: (831)
212-4355.
Pile caps for C-25; C-43; C-7; C-31A; C-31B; C-46; C-42; C-8 - OK highlight in
blue on page C2.1 (total of 8 pile caps)

 
104 REBAR
Assigned to: Date requested: 11/7/2017
Done by: Date due: 11/13/2017
Status: Cancelled Date done: 11/13/2017

Disp set to [CNCL] by a contractor via Hello! on 11/13/2017 at 07:10:08.
 
104 REBAR
Assigned to: Date requested: 11/9/2017
Done by: Date due: 11/15/2017
Status: Cancelled Date done: 11/15/2017

Scheduled by a contractor via Hello! on 11/09/2017 at 08:47:25. Contact: (831)
212-4355.

11/15 CNCL per Cameron//TYA

 
104 REBAR
Assigned to: Date requested: 11/13/2017
Done by: Date due: 11/17/2017
Status: Fail Date done: 11/17/2017

Scheduled by a contractor via Hello! on 11/13/2017 at 07:11:58. Contact: (831)
212-4355.
Pile caps C48; C9; C10; C32; C21; C22; C23 and adjacent grade beams
inspected. Pending on special inspector approval

 
101 FOUNDATION
Assigned to: Not Assigned Date requested: 11/15/2017
Done by: Date due: 11/22/2017
Status: Cancelled Date done: 11/21/2017

Scheduled by a contractor via Hello! on 11/15/2017 at 08:30:04. Contact: (831)
212-4355.

11/21 CNCL per Cameron//TYA

 
101 FOUNDATION
Assigned to: Date requested: 11/16/2017
Done by: Date due: 11/20/2017
Status: Partial Approval Date done: 11/20/2017
 


Scheduled by a contractor via Hello! on 11/16/2017 at 08:51:48. Contact: (831)
212-4355.
Changed date to 11/20/17- LMAN follow up for KHEY
Pilecaps at C22,23,24,32, C9/48, C10/21, OK.

 
104 REBAR
Assigned to: Date requested: 11/21/2017
Done by: Date due: 11/29/2017
Status: Partial Approval Date done: 11/29/2017

Scheduled by a contractor via Hello! on 11/21/2017 at 08:00:44. Contact: (831)
212-4355.
Pile caps C41B; C41; C20; C11; C49; C3; C33 (total of 7) -OK highlighted in
blue on page S2.1

 
101 FOUNDATION
Assigned to: Date requested: 11/27/2017
Done by: Date due: 12/1/2017
Status: Cancelled Date done: 12/1/2017

Scheduled by a contractor via Hello! on 11/27/2017 at 14:09:32. Contact: (831)
212-4355.
Cncl'd per phone call from Cameron. // JUES

 
104 REBAR
Assigned to: Date requested: 12/1/2017
Done by: Date due: 12/5/2017
Status: Fail Date done: 12/5/2017

Scheduled by a contractor via Hello! on 12/01/2017 at 07:20:20. Contact: (831)
212-4355.

1)Double pile cap shall have continuous reinforcement or RFI from EOR shall
be provided if not applicable
2)Grade beam reinforcement shall have min 12" embedment into pile cap (per
plan)
3)Spiral reinforcement around T Head bars shall have 2" clearance between the
bars
4)All reinforcement shall be clean of any concrete residual.
5)Provide RFI from EOR for pile cap installation regarding max distance from
top of the concrete to reinforcement

 
104 REBAR
Assigned to: Date requested: 12/4/2017
Done by: Date due: 12/6/2017
Status: Partial Approval Date done: 12/6/2017

Scheduled by a contractor via Hello! on 12/04/2017 at 12:58:11. Contact: (831)
212-4355.
Pile caps (total of 12) C34; C35; C50; C36B; LB2; C2; LB1; C12; C12B; C18;
C19; C40 -OK see highlight in orange on page C2.1

 
104 REBAR
Assigned to: Date requested: 12/5/2017
Done by: Date due: 12/7/2017
Status: Fail Date done: 12/7/2017

Scheduled by a contractor via Hello! on 12/05/2017 at 08:47:42. Contact: (831)
212-4355.
No one at the job side during inspection time frame

 
104 REBAR
Assigned to: Not Assigned Date requested: 12/5/2017
Done by: Date due: 12/7/2017
Status: Cancelled Date done: 12/5/2017
 


Scheduled by a contractor via Hello! on 12/05/2017 at 08:50:00. Contact: (831)
212-4355.

12/5 - cancelled because duplicate. //VNG

 
104 REBAR
Assigned to: Date requested: 12/6/2017
Done by: Date due: 12/8/2017
Status: Partial Approval Date done: 12/8/2017

Scheduled by a contractor via Hello! on 12/06/2017 at 08:27:14. Contact: (831)
212-4355.
Pile Caps: 51,36,1,58,57,56,13,37,17,39,14,15,15B,38, OK. Reinforcing steel,
Bolts/Plates, OK.
Note: Structural Observation letter to be provided prior to placement of
concrete.

 
104 REBAR
Assigned to: Date requested: 12/7/2017
Done by: Date due: 12/12/2017
Status: Cancelled Date done: 12/12/2017

Scheduled by a contractor via Hello! on 12/07/2017 at 14:13:49. Contact: (831)
212-4355.

12/12 CNCL per cameron//TYA

 
104 REBAR
Assigned to: Date requested: 12/11/2017
Done by: Date due: 12/13/2017
Status: Partial Approval Date done: 12/13/2017

Scheduled by a contractor via Hello! on 12/11/2017 at 08:21:22. Contact: (831)
212-4355.
Reinforcement for pile caps and adjacent grade beams, plates/bolts for TR1A;
C52; TR2A; C53; C55-OK highlighted in blue on page S2.1

 
104 REBAR
Assigned to: Date requested: 12/13/2017
Done by: Date due: 12/18/2017
Status: Cancelled Date done: 12/18/2017

Scheduled by a contractor via Hello! on 12/13/2017 at 17:56:52. Contact: (831)
212-4355.
Cameron

 
104 REBAR
Assigned to: Date requested: 12/14/2017
Done by: Date due: 12/19/2017
Status: Partial Approval Date done: 12/19/2017

Scheduled by a contractor via Hello! on 12/14/2017 at 14:43:54. Contact: (831)
212-4355.
Pile cap with bolts and plates TR1B & C54 -OK see highlight in pink on page
S2.1

 
601a REVISIONS SUBMITTED
Assigned to: Ket Le Received: 1/5/2018
Done by: Ket Le
Status: Done Completed: 1/16/2018
 


3 plans and calcs at pending area. KLE emailed to Lowell:
Hi Lowell,

I have approved the "foundation & structural" plans (which you submitted on
1/5/18) for the Building Department for the above noted permit case and I have
given the plans to our permit center staff to process to be ready for permit
issuance.

Please verify and obtain approvals from Fire Dept and Planning Dept for these
plans. In our permit tracking system, Fire Dept had noted "Foundation only OK
to release" ON 9/20/17. Planning Dept had approved previously on 9/29/17 but
it is not clear whether this approval is for the entire project.

Please contact and work with our permit center staff to make sure the plans
are ready before you come in to pull the permit. You can also contact them for
any fee related questions.

Ket Le
Plan Checker, Building Department
City of Santa Clara
(408) 615-2437 - Phone

KLE: Revision resubmittal, routed Three sets of plans, structural calcs and
response to comments

 
101 FOUNDATION
Assigned to: Date requested: 1/18/2018
Done by: Date due: 1/22/2018
Status: Fail Date done: 1/22/2018

Scheduled by a contractor via Hello! on 01/18/2018 at 10:38:47. Contact: (831)
212-4355.
Footings for retaining wall weren┐t inspected by special inspector r

 
104 REBAR
Assigned to: Date requested: 1/22/2018
Done by: Date due: 1/24/2018
Status: Partial Approval Date done: 1/24/2018

Scheduled by a contractor via Hello! on 01/22/2018 at 09:16:59. Contact: (831)
212-4355.
Footings for retaining wall -OK see highlight in yellow on page A1.1
Bridge abutment footings -OK see highlight in yellow on page A1.2

 
104 REBAR
Assigned to: Not Assigned Date requested: 1/24/2018
Done by: Date due: 1/30/2018
Status: Cancelled Date done: 1/25/2018

Disp set to [CNCL] by a contractor via Hello! on 01/25/2018 at 13:55:11.
 
634 FIRE, CLEAR W/ COND
Assigned to: Not Assigned INITIAL: 1/25/2018
Done by:
Status: Done RELEASE: 5/31/2018
 
 
104 REBAR
Assigned to: Date requested: 1/26/2018
Done by: Date due: 1/31/2018
Status: Partial Approval Date done: 1/31/2018

Scheduled by a contractor via Hello! on 01/26/2018 at 11:01:02. Contact: (831)
212-4355.
Reinforcement for retaining walls -OK
Footings for fast lane bridge (total of 6) -OK
See highlights in pink on page A1.1

 

 
662 BLDG ELEC REV COMMENTS
Assigned to: Not Assigned DATE ASSIGNED: 1/29/2018
Done by: DATE SENT:
Status: Done RESPONSE: 1/29/2018

(2) ses to KLE.
 
672 BLDG PLM REV COMMENT
Assigned to: Not Assigned DATE ASSIGNED: 1/29/2018
Done by: DATE SENT:
Status: Done RESPONSE: 1/29/2018
 
 
682 BLDG MECH REV COMMENTS
Assigned to: Not Assigned DATE ASSIGNED: 1/29/2018
Done by: DATE SENT:
Status: Done RESPONSE: 1/29/2018
 
 
605 REC'D THIRD PTY APP PLNS
Assigned to: Ket Le 1/29/2018
Done by: Ket Le
Status: Done Received: 2/1/2018

2 plans at pending area. KLE approved for full permit issuance.///
*2 sets of complete approved plans with elec, mech, plumb, have been
submitted. Plans have been approved by trades and all routed to KLE. Contact:
Lowell (408) 986-5874 or lowell.esposo@CAGreatAmerica.com*Planning review
sign off required.

 
612 PLANNING REVIEW
Assigned to: Not Assigned DATE SENT: 1/29/2018
Done by: Ket Le RECEIVED:
Status: Done COMPLETE: 2/1/2018

1-31-18: JSCH signed off on plans.///
*2 sets of complete approved plans with elec, mech, plumb, have been
submitted. Plans have been approved by trades and all routed to KLE. Contact:
Lowell (408) 986-5874 or lowell.esposo@CAGreatAmerica.com*Planning review
sign off required.

 
104 REBAR
Assigned to: Date requested: 1/30/2018
Done by: Date due: 2/2/2018
Status: Cancelled Date done: 2/1/2018

Scheduled by a contractor via Hello! on 01/30/2018 at 10:29:41. Contact: (831)
212-4355.

2/1 - Canceled per Cameron Kinder. //MPEY

 
104 REBAR
Assigned to: Date requested: 2/1/2018
Done by: Date due: 2/6/2018
Status: Partial Approval Date done: 2/6/2018

Scheduled by a contractor via Hello! on 02/01/2018 at 10:51:46. Contact: (831)
212-4355.
Reinforcement for footingsat Fast Lane completed -OK see highlights in green
on page A1.1 (total 11)
Reinforcement for fast lane bridge columns/piers highlighted in pink on page
A1.1 -OK

 
104 REBAR
Assigned to: Date requested: 2/5/2018
Done by: Date due: 2/8/2018
Status: Partial Approval Date done: 2/9/2018
 


Scheduled by a contractor via Hello! on 02/05/2018 at 20:50:50. Contact: (831)
212-4355.
Reinforcement for slab on grade for new building -OK

 
104 REBAR
Assigned to: Date requested: 2/12/2018
Done by: Date due: 2/14/2018
Status: Partial Approval Date done: 2/14/2018

Scheduled by a contractor via Hello! on 02/12/2018 at 07:08:49. Contact: (831)
212-4355.


Rest of the columns reinforcement for fast lane bridge -OK see page A1.1

 
104 REBAR
Assigned to: Date requested: 2/12/2018
Done by: Date due: 2/16/2018
Status: Partial Approval Date done: 2/16/2018

Scheduled by a contractor via Hello! on 02/12/2018 at 15:20:34. Contact: (831)
212-4355.
The upper rock slab starts at pier cap C-11 and extend North to pier cap C-8.
highlighted in blue. The West double mat area is to be located 7' North of pier
cap C-48 and the East double mat is to start 4'3" South of pier cap C-9.
Main building slab reinforcement -OK see highlight in yellow on page S 2.0

 
303 STORM DRAIN
Assigned to: Date requested: 2/14/2018
Done by: Target Date: 2/15/2018
Status: Partial Approval Date done: 2/14/2018

15' SD on page C4.1 from RIM 17.75 to Pond INV 12.84 -OK highlighted in
yellow

 
302 UNDERFLOOR PLUMBING
Assigned to: Date requested: 2/14/2018
Done by: Target Date: 2/15/2018
Status: Fail Date done: 2/14/2018

under slab drain line shall be pressure tested and have and of the run clean out
 
104 REBAR
Assigned to: Date requested: 2/16/2018
Done by: Date due: 2/21/2018
Status: Cancelled Date done: 2/20/2018

Disp set to [CNCL] by a contractor via Hello! on 02/20/2018 at 16:03:56.
 
104 REBAR
Assigned to: Date requested: 2/20/2018
Done by: Date due: 2/23/2018
Status: Partial Approval Date done: 2/23/2018

Scheduled by a contractor via Hello! on 02/20/2018 at 16:05:16. Contact: (831)
212-4355.
Reinforcing steel at 'queue' tunnel (S5.4/11); The Station-(S5.2/Det.13;
Lauchpad (S5.2/11); North rock structure reinforcement for shotcrete
(RW-9/Det.4), OK.

 
104 REBAR
Assigned to: Date requested: 2/22/2018
Done by: Date due: 2/26/2018
Status: Fail Date done: 2/26/2018

Scheduled by a contractor via Hello! on 02/22/2018 at 10:17:16. Contact: (831)
212-4355.
Inspection declined by contractor (Cameron Kinder)

 

 
104 REBAR
Assigned to: Date requested: 2/26/2018
Done by: Date due: 2/28/2018
Status: Fail Date done: 2/28/2018

Scheduled by a contractor via Hello! on 02/26/2018 at 07:34:59. Contact: (831)
212-4355.

Cameron moved from AM to PM. // JUES
not ready ( need to provide special inspector report)

 
104 REBAR
Assigned to: Date requested: 2/28/2018
Done by: Date due: 3/2/2018
Status: Partial Approval Date done: 3/2/2018

Scheduled by a contractor via Hello! on 02/28/2018 at 07:25:46. Contact: (831)
212-4355.
Footings for station building at East and North of the building -OK see highlight
in yellow on page S 2.0

 
104 REBAR
Assigned to: Date requested: 3/1/2018
Done by: Date due: 3/6/2018
Status: Partial Approval Date done: 3/6/2018

Scheduled by a contractor via Hello! on 03/01/2018 at 15:11:04. Contact: (831)
212-4355.
Mat slab reinforcement for station building -OK
Reinforcement for lower section of rockwall -OK
see highlights in yellow on pages RW-2 &S2.0
Queue tunel walls - reinforcement OK see highlight in green on page A1.2

 
104 REBAR
Assigned to: Date requested: 3/2/2018
Done by: Date due: 3/6/2018
Status: Cancelled Date done: 3/6/2018

Scheduled by a contractor via Hello! on 03/02/2018 at 09:13:33. Contact: (520)
310-0773.

 
104 REBAR
Assigned to: Date requested: 3/5/2018
Done by: Date due: 3/7/2018
Status: Cancelled Date done: 3/7/2018

Scheduled by a contractor via Hello! on 03/05/2018 at 07:41:28. Contact: (831)
212-4355.

 
104 REBAR
Assigned to: Date requested: 3/6/2018
Done by: Date due: 3/9/2018
Status: Cancelled Date done: 3/9/2018

Scheduled by a contractor via Hello! on 03/06/2018 at 19:00:21. Contact: (831)
212-4355.

 
104 REBAR
Assigned to: Date requested: 3/12/2018
Done by: Date due: 3/15/2018
Status: Partial Approval Date done: 3/16/2018

Scheduled by a contractor via Hello! on 03/12/2018 at 07:34:33. Contact: (831)
212-4355.
Reinforcement for ride entry sign footings -OK
see highlight on page A1.2
See correction notice about Photo booth footings ( emailed on 3/15/18 to the
contractor)

 

 
104 REBAR
Assigned to: Date requested: 3/13/2018
Done by: Date due: 3/16/2018
Status: Cancelled Date done: 3/16/2018

Disp set to [CNCL] by a contractor via Hello! on 03/16/2018 at 07:34:45.
 
104 REBAR
Assigned to: Date requested: 3/15/2018
Done by: Date due: 3/20/2018
Status: Cancelled Date done: 3/20/2018

Scheduled by a contractor via Hello! on 03/15/2018 at 16:34:39. Contact: (831)
212-4355.

 
104 REBAR
Assigned to: Date requested: 3/16/2018
Done by: Date due: 3/21/2018
Status: Cancelled Date done: 3/21/2018

Scheduled by a contractor via Hello! on 03/16/2018 at 16:17:16. Contact: (520)
310-0773.
canceled per contractor request

 
116 ROOF NAILING
Assigned to: Date requested: 3/21/2018
Done by: Target Date: 3/26/2018
Status: Fail Date done: 3/26/2018

Scheduled by a contractor via Hello! on 03/21/2018 at 12:09:27. Contact: (831)
212-4355.

No access:
No latter available, and no lift available for roof access to complete inspection.

 
104 REBAR
Assigned to: Date requested: 3/22/2018
Done by: Date due: 3/27/2018
Status: Partial Approval Date done: 3/27/2018

Scheduled by a contractor via Hello! on 03/22/2018 at 14:28:21. Contact: (520)
310-0773.
Rock tunel at open cave -reinforcement OK see highlight in yellow on page
RW-2

 
116 ROOF NAILING
Assigned to: Date requested: 3/26/2018
Done by: Target Date: 3/27/2018
Status: Fail Date done: 3/27/2018

Scheduled by a contractor via Hello! on 03/21/2018 at 12:09:27. Contact: (831)
212-4355.

3/26 - Added per LMAN. //MPEY
roof framing doesn't match approved plan details

 
104 REBAR
Assigned to: Date requested: 3/27/2018
Done by: Date due: 4/2/2018
Status: Partial Approval Date done: 4/2/2018

Scheduled by a contractor via Hello! on 03/27/2018 at 07:53:52. Contact: (831)
212-4355.
Satiates A1.1/A1.2- reinforcing steel at compressor pad, and at stairways at
Que tunnel, ok.

 

 
118 ROUGH FRAME
Assigned to: Date requested: 3/29/2018
Done by: Target Date: 4/4/2018
Status: Fail Date done: 4/4/2018

Scheduled by a contractor via Hello! on 03/29/2018 at 09:52:17. Contact: (831)
212-4355.
Approved details for Station Building framing shall be at the job site during
inspection

 
302 UNDERFLOOR PLUMBING
Assigned to: Date requested: 4/2/2018
Done by: Target Date: 4/5/2018
Status: Cancelled Date done: 4/5/2018

Scheduled by a contractor via Hello! on 04/02/2018 at 09:04:59. Contact: (831)
212-4355.

 
210 ROUGH ELECTRICAL
Assigned to: Date Requested: 4/4/2018
Done by: Target Date: 4/5/2018
Status: Partial Approval Date Received: 4/5/2018

Scheduled by a contractor via Hello! on 04/04/2018 at 12:27:29. Contact: (831)
212-4355.
Rough electrical for Station Building-OK

 
116 ROOF NAILING
Assigned to: Date requested: 4/4/2018
Done by: Target Date: 4/5/2018
Status: Partial Approval Date done: 4/4/2018

Roof nailing for Station Building -OK
 
301 UNDERGROUND PLUMBING
Assigned to: Date requested:
Done by: Target Date:
Status: Partial Approval Date done: 4/5/2018

Underground Water line from storage track to Station Building-OK
Underground air line-OK

 
118 ROUGH FRAME
Assigned to: Date requested:
Done by: Target Date:
Status: Partial Approval Date done: 4/5/2018

Framing for Station Building-OK
 
104 REBAR
Assigned to: Date requested: 4/6/2018
Done by: Date due: 4/9/2018
Status: Partial Approval Date done: 4/9/2018

Scheduled by a contractor via Hello! on 04/06/2018 at 10:53:12. Contact: (831)
212-4355.
6 piers for canopy, OK, pending special inspection report for dewatering
process during placement.

 
116 ROOF NAILING
Assigned to: Date requested: 4/9/2018
Done by: Target Date: 4/10/2018
Status: Passed Date done: 4/10/2018

Scheduled by a contractor via Hello! on 04/09/2018 at 15:01:20. Contact: (831)
212-4355.
Roof nailing for photo booth-OK

 

 
115 EXTERIOR SHEAR
Assigned to: Date requested: 4/10/2018
Done by: Target Date: 4/12/2018
Status: Partial Approval Date done: 4/12/2018

Scheduled by a contractor via Hello! on 04/10/2018 at 14:12:54. Contact: (831)
212-4355.
Ride photo booth exterior shear walls OK

 
502 INSULATION
Assigned to: Date requested: 4/10/2018
Done by: Target Date: 4/16/2018
Status: Passed Date done: 4/16/2018

Scheduled by a contractor via Hello! on 04/10/2018 at 14:13:41. Contact: (831)
212-4355.

 
210 ROUGH ELECTRICAL
Assigned to: Date Requested: 4/10/2018
Done by: Target Date: 4/12/2018
Status: Partial Approval Date Received: 4/12/2018

Scheduled by a contractor via Hello! on 04/10/2018 at 14:14:32. Contact: (831)
212-4355.
Ride photo booth rough electrical OK

 
407 ROUGH MECHANICAL
Assigned to: Date requested: 4/10/2018
Done by: Target Date: 4/12/2018
Status: Fail Date done: 4/12/2018

Scheduled by a contractor via Hello! on 04/10/2018 at 14:16:00. Contact: (831)
212-4355.
not ready

 
303 STORM DRAIN
Assigned to: Date requested: 4/11/2018
Done by: Target Date: 4/16/2018
Status: Cancelled Date done: 4/16/2018

Scheduled by a contractor via Hello! on 04/11/2018 at 09:20:18. Contact: (831)
212-4355.

 
502 INSULATION
Assigned to: Not Assigned Date requested: 4/11/2018
Done by: Target Date: 4/16/2018
Status: Cancelled Date done: 4/11/2018

Scheduled by a contractor via Hello! on 04/11/2018 at 09:21:04. Contact: (831)
212-4355.

 
401 UNDERGROUND MECHANICAL
Assigned to: Date requested: 4/11/2018
Done by: Target Date: 4/12/2018
Status: Cancelled Date done: 4/12/2018

Scheduled by a contractor via Hello! on 04/11/2018 at 09:22:34. Contact: (831)
212-4355.
not applicalble

 
118 ROUGH FRAME
Assigned to: Date requested: 4/11/2018
Done by: Target Date: 4/12/2018
Status: Partial Approval Date done: 4/12/2018

Scheduled by a contractor via Hello! on 04/11/2018 at 09:21:04. Contact: (831)
212-4355.
Ride photo booth rough frame OK

 

 
131 DRYWALL
Assigned to: Date Requested: 4/11/2018
Done by: Target Date: 4/12/2018
Status: Fail Date Received: 4/12/2018

Scheduled by a contractor via Hello! on 04/11/2018 at 09:21:04. Contact: (831)
212-4355.
not ready

 
203 UNDERGROUND ELECTRICAL
Assigned to: Date Requested: 4/11/2018
Done by: Target Date: 4/12/2018
Status: Cancelled Date Received: 4/12/2018

Scheduled by a contractor via Hello! on 04/11/2018 at 09:21:04. Contact: (831)
212-4355.
Wrong inspection scheduled

 
115 EXTERIOR SHEAR
Assigned to: Date requested: 4/16/2018
Done by: Target Date: 4/19/2018
Status: Fail Date done: 4/20/2018

Scheduled by a contractor via Hello! on 04/16/2018 at 09:56:05. Contact: (831)
212-4355.
not ready

 
118 ROUGH FRAME
Assigned to: Date requested: 4/16/2018
Done by: Target Date: 4/19/2018
Status: Passed Date done: 4/20/2018

Scheduled by a contractor via Hello! on 04/16/2018 at 09:57:15. Contact: (831)
212-4355.

 
210 ROUGH ELECTRICAL
Assigned to: Date Requested: 4/16/2018
Done by: Target Date: 4/19/2018
Status: Fail Date Received: 4/20/2018

Scheduled by a contractor via Hello! on 04/16/2018 at 09:58:28. Contact: (831)
212-4355.
not ready

 
118 ROUGH FRAME
Assigned to: Date requested:
Done by: Target Date:
Status: Passed Date done: 4/16/2018

Frame for compressor addition-OK
 
399 PLUMBING FINAL
Assigned to: Date requested: 5/24/2018
Done by: Target Date: 5/25/2018
Status: Passed Date done: 5/25/2018

Scheduled by a contractor via Hello! on 05/24/2018 at 09:41:06. Contact: (831)
212-4355.

 
499 MECHANICAL FINAL
Assigned to: Date requested: 5/24/2018
Done by: Target Date: 5/25/2018
Status: Passed Date done: 5/25/2018

Scheduled by a contractor via Hello! on 05/24/2018 at 09:42:44. Contact: (831)
212-4355.

 

 
299 ELECTRICAL FINAL
Assigned to: Date Requested: 5/24/2018
Done by: Target Date: 5/25/2018
Status: Passed Date Received: 5/25/2018

Scheduled by a contractor via Hello! on 05/24/2018 at 09:44:08. Contact: (831)
212-4355.

 
599 BUILDING FINAL
Assigned to: Date requested: 5/31/2018
Done by: Target Date: 6/1/2018
Status: Fail Date done: 6/1/2018

Scheduled by a contractor via Hello! on 05/31/2018 at 12:50:11. Contact: (408)
507-6430.
Tag: Service counter at 35 inches, AOR to address and provide revision

TAG:

 
599 BUILDING FINAL
Assigned to: Date requested: 6/4/2018
Done by: Target Date: 6/5/2018
Status: Passed Date done: 6/5/2018

Scheduled by a contractor via Hello! on 06/04/2018 at 11:23:39. Contact: (408)
507-6430.

Fees
Item Fee Amount Fee Remaining
Plumbing Permit $50.00 $0.00
Mechanical Permit $80.75 $0.00
Microfilm $90.00 $0.00
Microfilm $190.00 $0.00
Building Standards $248.00 $0.00
Microfilm $470.00 $0.00
Electrical Permit $492.25 $0.00
Seismic (Commercial) $1,736.00 $0.00
Bldg Permit - Adv Planning Fee $3,690.17 $0.00
Plan Review Fire $6,150.28 $0.00
Phased Review 3rd w/o T24 $18,450.83 $0.00
Building Permit $24,601.10 $0.00