Logo   City of Santa Clara Smart Permit Center logo
Home Status Parcel Comment Apply Help

View Case Status

The information below summarizes the case you selected.

Case Number: BLD2017-47984
 
Status: Partial Permit
Name: CALIFORNIA'S GREAT AMERICA
Address:
 
Application Date: 9/1/2017
Description: 3RD PARTY STRUCTURAL/FOUNDATION ONLY -
CONSTRUCTION OF (N) SUPERSTRUCTURE COASTER,
CALLED "RAILBLAZER", NEW BUILDING # 541 REQUESTED
 
Activities

 
APPLICATION RECEIVED
Assigned to: Not Assigned
Done by:
Status: Done Date Received: 9/1/2017

Created by Online Portal on 09/01/2017 at 16:17 PM
 
603 THIRD PARTY PLAN CHECK
Assigned to: Ket Le Sent to 3rd Pty: 9/1/2017
Done by: Ket Le 3rd Pty Appr.:
Status: Done Appr. plans rec'd: 9/29/2017

ONLINE STRUCTURAL 3RD PARTY REVIEW - BOLEY
 
608d BLDG PLAN REV REG.
Assigned to: Ket Le SUBMITTAL: 9/1/2017
Done by: Ket Le TARGET: 10/3/2017
Status: Done END DATE: 9/29/2017

ONLINE STRUCTURAL 3RD PARTY REVIEW - BOLEY
 
612 PLANNING REVIEW
Assigned to: DATE SENT: 9/1/2017
Done by: RECEIVED: 9/1/2017
Status: Done COMPLETE: 9/29/2017

ONLINE - Stamp transfer required
 
632 FIRE REVIEW
Assigned to: Not Assigned DATE SENT: 9/1/2017
Done by: Not Completed RECEIVED: 9/1/2017
Status: COMPLETE:

ONLINE - copy of receipt and print screen in pick up.
 
652 WATER REVIEW
Assigned to: Not Assigned DATE SENT: 9/1/2017
Done by: RECEIVED: 9/1/2017
Status: Done COMPLETE: 9/27/2017

09/27/17 - OK to issue permit. No requirements from Water Dept. Per site visit
BFPs are above ground. HM

ONLINE

 
642 ENGR REVIEW
Assigned to: Not Assigned DATE SENT: 9/1/2017
Done by: RECEIVED: 9/1/2017
Status: Done COMPLETE: 9/6/2017

NEDRAT

ONLINE

 
601a REVISIONS SUBMITTED
Assigned to: Ket Le Received: 9/13/2017
Done by: Ket Le
Status: Done Completed: 9/29/2017

KLE, routed 3 sets of plans (REVISIONS), 2 sets of calcs- Foundation, 2 sets
of calcs- Section C Foundation, 2 sets of calcs- Column Anchorage, 1 set C-10
Form

Contact: Lowell Esposo, 408-986-5874, lowell.esposo@cagreatamerica.com

 
633 FIRE REVIEW COMMENTS
Assigned to: Not Assigned DATE SENT: 9/20/2017
Done by:
Status: Done RESPONSE: 9/20/2017

Foundation only OK to release - DP

 
(F) ISSUE PARTIAL PERMIT
Assigned to: Not Assigned
Done by: 10/3/2017
Status: Done Date issued: 10/3/2017
 
 
104 REBAR
Assigned to: Date requested: 10/11/2017
Done by: Date due: 10/16/2017
Status: Partial Approval Date done: 10/17/2017

Scheduled by a contractor via Hello! on 10/11/2017 at 08:38:47. Contact: (831)
212-4355.
Cages # C5; C6; C25; C26; C27; C28; C29; C30; C44; C45; C47; C43; C8; C4;
C31A; C42 and C46 total of 17 cages -OK highlight in yellow on page S2.1

 
101 FOUNDATION
Assigned to: Date requested: 10/13/2017
Done by: Date due: 10/17/2017
Status: Partial Approval Date done: 10/17/2017

Scheduled by a contractor via Hello! on 10/13/2017 at 08:56:43. Contact: (831)
212-4355.
Cages # C3; C7; C9; C10; C21; C2822; C23; C32; C33; C48; C49 total of 11
cages -OK highlight in green on page S2.1

 
101 FOUNDATION
Assigned to: Date requested: 10/16/2017
Done by: Date due: 10/18/2017
Status: Fail Date done: 10/18/2017

Scheduled by a contractor via Hello! on 10/16/2017 at 07:25:43. Contact: (831)
212-4355.
not ready

 
104 REBAR
Assigned to: Date requested: 10/17/2017
Done by: Date due: 10/20/2017
Status: Partial Approval Date done: 10/20/2017

Scheduled by a contractor via Hello! on 10/17/2017 at 09:22:20. Contact: (831)
212-4355.
Total of 24 cages C34; C11; C20; C41; C41B; C40; C19; C12; C2; C50; C35;
C36B; LB2; C12B; C18; C1; C36; C51; C58; C13; C17; C57; C15B; C56 - OK
see page S2.1 highlight in orange

 
104 REBAR
Assigned to: Date requested: 10/18/2017
Done by: Date due: 10/23/2017
Status: Cancelled Date done: 10/20/2017

Disp set to [CNCL] by a contractor via Hello! on 10/20/2017 at 13:59:38.
 
101 FOUNDATION
Assigned to: Date requested: 10/19/2017
Done by: Date due: 10/24/2017
Status: Cancelled Date done: 10/23/2017

Scheduled by a contractor via Hello! on 10/19/2017 at 13:22:24. Contact: (831)
212-4355.

10/23 - Canceled per Cameron Kinder. //MPEY

 
104 REBAR
Assigned to: Date requested: 10/20/2017
Done by: Date due: 10/25/2017
Status: Partial Approval Date done: 10/25/2017
 


Scheduled by a contractor via Hello! on 10/20/2017 at 14:01:04. Contact: (831)
212-4355.
reinforcing cages, per specifications- 10 locations OK, as noted on card, and
see pink highlighting for locations.

 
104 REBAR
Assigned to: Date requested: 10/23/2017
Done by: Date due: 10/27/2017
Status: Partial Approval Date done: 10/27/2017

Scheduled by a contractor via Hello! on 10/23/2017 at 15:06:46. Contact: (831)
212-4355.
9 spiral cages/caisons OK as indicated on permit card, and highlighting on
plans.

 
104 REBAR
Assigned to: Date requested: 10/25/2017
Done by: Date due: 10/30/2017
Status: Fail Date done: 10/30/2017

Scheduled by a contractor via Hello! on 10/25/2017 at 09:16:02. Contact: (831)
212-4355.
Contractor declined inspection

Not ready:

 
101 FOUNDATION
Assigned to: Date requested: 10/27/2017
Done by: Date due: 11/1/2017
Status: Partial Approval Date done: 11/1/2017

Scheduled by a contractor via Hello! on 10/27/2017 at 10:59:21. Contact: (831)
212-4355.
Pile caps and grade beams for piles C27; C45; C44; C26; C6; C28; C5; C29;
C30 (total of 9) - OK highlight in green on page C2.1
No conduits allowed to install along grade beam without EOR approval

 
101 FOUNDATION
Assigned to: Date requested: 10/30/2017
Done by: Date due: 11/2/2017
Status: Fail Date done: 11/2/2017

Scheduled by a contractor via Hello! on 10/30/2017 at 08:12:56. Contact: (831)
212-4355.

Not ready:

 
104 REBAR
Assigned to: Date requested: 11/2/2017
Done by: Date due: 11/7/2017
Status: Fail Date done: 11/7/2017

Scheduled by a contractor via Hello! on 11/02/2017 at 15:06:01. Contact: (831)
212-4355.

Not ready:

 
104 REBAR
Assigned to: Date requested: 11/3/2017
Done by: Date due: 11/8/2017
Status: Fail Date done: 11/8/2017
 


Scheduled by a contractor via Hello! on 11/03/2017 at 14:50:15. Contact: (831)
212-4355.
Pile cap located off set of C4 pile- Provide RFI from EOR
Provide RFI from EOR regarding conduits running inside along the grade beam
Grade beam excavation shall be clean of any loose dirt and have min 3
clearance to earth
All grade beams reinforcement into pile cap shall be completed prior inspection
n

 
101 FOUNDATION
Assigned to: Date requested: 11/6/2017
Done by: Date due: 11/9/2017
Status: Partial Approval Date done: 11/9/2017

Scheduled by a contractor via Hello! on 11/06/2017 at 09:44:13. Contact: (831)
212-4355.
Pile caps for C-25; C-43; C-7; C-31A; C-31B; C-46; C-42; C-8 - OK highlight in
blue on page C2.1 (total of 8 pile caps)

 
104 REBAR
Assigned to: Date requested: 11/7/2017
Done by: Date due: 11/13/2017
Status: Cancelled Date done: 11/13/2017

Disp set to [CNCL] by a contractor via Hello! on 11/13/2017 at 07:10:08.
 
104 REBAR
Assigned to: Date requested: 11/9/2017
Done by: Date due: 11/15/2017
Status: Cancelled Date done: 11/15/2017

Scheduled by a contractor via Hello! on 11/09/2017 at 08:47:25. Contact: (831)
212-4355.

11/15 CNCL per Cameron//TYA

 
104 REBAR
Assigned to: Date requested: 11/13/2017
Done by: Date due: 11/17/2017
Status: Fail Date done: 11/17/2017

Scheduled by a contractor via Hello! on 11/13/2017 at 07:11:58. Contact: (831)
212-4355.
Pile caps C48; C9; C10; C32; C21; C22; C23 and adjacent grade beams
inspected. Pending on special inspector approval

 
101 FOUNDATION
Assigned to: Not Assigned Date requested: 11/15/2017
Done by: Date due: 11/22/2017
Status: Cancelled Date done: 11/21/2017

Scheduled by a contractor via Hello! on 11/15/2017 at 08:30:04. Contact: (831)
212-4355.

11/21 CNCL per Cameron//TYA

 
101 FOUNDATION
Assigned to: Date requested: 11/16/2017
Done by: Date due: 11/20/2017
Status: Partial Approval Date done: 11/20/2017

Scheduled by a contractor via Hello! on 11/16/2017 at 08:51:48. Contact: (831)
212-4355.
Changed date to 11/20/17- LMAN follow up for KHEY
Pilecaps at C22,23,24,32, C9/48, C10/21, OK.

 

 
104 REBAR
Assigned to: Date requested: 11/21/2017
Done by: Date due: 11/29/2017
Status: Partial Approval Date done: 11/29/2017

Scheduled by a contractor via Hello! on 11/21/2017 at 08:00:44. Contact: (831)
212-4355.
Pile caps C41B; C41; C20; C11; C49; C3; C33 (total of 7) -OK highlighted in
blue on page S2.1

 
101 FOUNDATION
Assigned to: Date requested: 11/27/2017
Done by: Date due: 12/1/2017
Status: Cancelled Date done: 12/1/2017

Scheduled by a contractor via Hello! on 11/27/2017 at 14:09:32. Contact: (831)
212-4355.
Cncl'd per phone call from Cameron. // JUES

 
104 REBAR
Assigned to: Date requested: 12/1/2017
Done by: Date due: 12/5/2017
Status: Fail Date done: 12/5/2017

Scheduled by a contractor via Hello! on 12/01/2017 at 07:20:20. Contact: (831)
212-4355.

1)Double pile cap shall have continuous reinforcement or RFI from EOR shall
be provided if not applicable
2)Grade beam reinforcement shall have min 12" embedment into pile cap (per
plan)
3)Spiral reinforcement around T Head bars shall have 2" clearance between the
bars
4)All reinforcement shall be clean of any concrete residual.
5)Provide RFI from EOR for pile cap installation regarding max distance from
top of the concrete to reinforcement

 
104 REBAR
Assigned to: Date requested: 12/4/2017
Done by: Date due: 12/6/2017
Status: Partial Approval Date done: 12/6/2017

Scheduled by a contractor via Hello! on 12/04/2017 at 12:58:11. Contact: (831)
212-4355.
Pile caps (total of 12) C34; C35; C50; C36B; LB2; C2; LB1; C12; C12B; C18;
C19; C40 -OK see highlight in orange on page C2.1

 
104 REBAR
Assigned to: Date requested: 12/5/2017
Done by: Date due: 12/7/2017
Status: Fail Date done: 12/7/2017

Scheduled by a contractor via Hello! on 12/05/2017 at 08:47:42. Contact: (831)
212-4355.
No one at the job side during inspection time frame

 
104 REBAR
Assigned to: Not Assigned Date requested: 12/5/2017
Done by: Date due: 12/7/2017
Status: Cancelled Date done: 12/5/2017

Scheduled by a contractor via Hello! on 12/05/2017 at 08:50:00. Contact: (831)
212-4355.

12/5 - cancelled because duplicate. //VNG

 

 
104 REBAR
Assigned to: Date requested: 12/6/2017
Done by: Date due: 12/8/2017
Status: Partial Approval Date done: 12/8/2017

Scheduled by a contractor via Hello! on 12/06/2017 at 08:27:14. Contact: (831)
212-4355.
Pile Caps: 51,36,1,58,57,56,13,37,17,39,14,15,15B,38, OK. Reinforcing steel,
Bolts/Plates, OK.
Note: Structural Observation letter to be provided prior to placement of
concrete.

 
104 REBAR
Assigned to: Date requested: 12/7/2017
Done by: Date due: 12/12/2017
Status: Cancelled Date done: 12/12/2017

Scheduled by a contractor via Hello! on 12/07/2017 at 14:13:49. Contact: (831)
212-4355.

12/12 CNCL per cameron//TYA

 
104 REBAR
Assigned to: Date requested: 12/11/2017
Done by: Date due: 12/13/2017
Status: Partial Approval Date done: 12/13/2017

Scheduled by a contractor via Hello! on 12/11/2017 at 08:21:22. Contact: (831)
212-4355.
Reinforcement for pile caps and adjacent grade beams, plates/bolts for TR1A;
C52; TR2A; C53; C55-OK highlighted in blue on page S2.1

 
104 REBAR
Assigned to: Date requested: 12/13/2017
Done by: Not Completed Date due: 12/18/2017
Status: Scheduled Date done:

Scheduled by a contractor via Hello! on 12/13/2017 at 17:56:52. Contact: (831)
212-4355.

 
104 REBAR
Assigned to: Date requested: 12/14/2017
Done by: Not Completed Date due: 12/19/2017
Status: Scheduled Date done:

Scheduled by a contractor via Hello! on 12/14/2017 at 14:43:54. Contact: (831)
212-4355.

Fees
Item Fee Amount Fee Remaining
Microfilm $90.00 $0.00
Building Standards $248.00 $0.00
Seismic (Commercial) $1,736.00 $0.00
Bldg Permit - Adv Planning Fee $3,690.17 $0.00
Plan Review Fire $6,150.28 $0.00
Fast Track Review 3rd w/o T24 $18,450.83 $0.00
Building Permit $24,601.10 $0.00


What would you like to do next?

Back to Search
Top of Page 
Help